N.D. Cent. Code §47-04.1-16
—
Condominium Ownership — EV Charging Station Installation
Owner applications for EV charging station installation must be approved or denied in writing. If not denied within 60 days, the application is deemed approved. Insurance certificate required within 14 days of approval. Civil penalty for willful violation up to $1,000.
Reviewed · North Dakota changes feed
Compliance
| Ref | Requirement |
|---|---|
| If not denied within 60 days, the application is deemed approved. | |
| Owner applications for EV charging station installation must be approved or denied in writing. |
Disclosure
| Ref | Requirement |
|---|---|
| Insurance certificate required within 14 days of approval. |
Financial
| Ref | Requirement |
|---|---|
| Civil penalty for willful violation up to $1,000. |